Planning

The schedule is only useful if it is believed. This pillar builds the capability to produce a plan that holds, review it every day, and act on what it finds before the next shift starts.


Pillar Intent

The Planning pillar exists to ensure that the right work is scheduled, resourced, and sequenced, and that when reality diverges from the plan, the gap is visible, owned, and acted on the same day.

Most sites have a schedule. Fewer have a schedule that produces the right output.

The most common failure is not a missing schedule. It is a schedule shaped by the wrong objective. When a site is measured on volume, it learns to make what is easiest to make in the largest quantities. Long runs. Fewer changeovers. High output numbers. The metrics look good. But the wrong product is being made. The right product is short. Inventory of what nobody needs builds in the warehouse, taking up space, tying up cash, and creating handling and storage problems that nobody planned for. Meanwhile the customer is waiting.

The schedule did not fail. It delivered exactly what it was designed to deliver. The problem was what it was designed to deliver.

This pillar builds the capability to produce a schedule that is built around what is actually needed — and to hold that schedule against the pressure to optimise for something easier to measure. It also builds the capability to manage the exceptions that will always arise without collapsing the whole plan.

The Planning pillar owns one core process: the Integrated Schedule. It is reviewed daily, at every tier, using two questions that do not change.


Pillar Owned Losses

The Planning pillar is accountable for addressing these losses

⚠️
Wrong product produced, the schedule built around what is easiest to make rather than what is needed next. Long runs, fewer changeovers, volume metrics that look good while the right product goes short, the wrong product fills the warehouse, and the customer waits. Stockouts, excess inventory, and poor customer service are all consequences of this single failure.
⚠️
Unplanned downtime caused by maintenance that was not scheduled before the failure occurred, because the planning system never created the slot, or the slot was given back to production before the work could be done.
⚠️
Procurement failures, materials not available when the schedule requires them, because lead times were not built into the plan and the order was placed when the need was urgent rather than when it was foreseeable. Expediting cost is the price of this failure.
⚠️
Disconnection from the corporate demand signal, the site running to a plan that does not reflect what the business actually needs.
⚠️
Schedules built on wrong data, run rates, yields, cycle times, or material quantities that no longer reflect what the operation actually does, producing plans that cannot be met and variances that cannot be explained.

Pillar Owned Processes

The Planning pillar owns one process.

The Integrated Schedule

Not three separate schedules that are reconciled weekly. One integrated schedule that holds production, maintenance, and procurement together in a single picture, reviewed daily.

The same two questions are asked at every tier, every day:

1️⃣
Did we do what we said we would do? If yes, confirm and move on. If no, understand why. Not to assign blame, to understand what the system failed to provide. Was the resource not available? Was the material not there? Was the equipment not ready? The answer determines what needs to change before it happens again.
2️⃣
Do we have what we need to do what we need to do next? If yes, confirm the plan and protect it. If no, act now. Move things around. Find more resource. Find more time. Find an alternative. The question is not whether there is a problem — it is whether the problem is visible early enough to do something about it.

These two questions are the whole process. Everything else, the data, the boards, the meeting structure, exists to answer them accurately and in time to act.

What is reviewed at each tier

The Integrated Schedule sits inside the Tiered Accountability Meeting system. It is not a separate set of meetings. It is the schedule-specific content that each tier reviews as part of its standard agenda, using the same structure, the same two questions, and the same escalation logic as every other hypercare process.

Tier 1 — multiple meetings, one per line. Each line runs its own Tier 1. Operations and the maintenance person responsible for that area both attend. Operations and Maintenance review the schedule for the line, did the line run what was planned, is the next run resourced and ready, are there any gaps for this shift or the next. Did we complete planned work for the same area: is the slot still available, is access confirmed, are parts and resource in place.

A production delay that puts a maintenance slot at risk is known immediately, not discovered when maintenance arrives and the line is still running. Problems are named here. What can be resolved at the line is resolved. What cannot is escalated to Tier 2.

Tier 2 — two parallel meetings, both feeding Tier 3. Tier 2 runs as two separate meetings, each consolidating the picture from their Tier 1s. This allows for prioritisation within the function.

Operations Tier 2 brings together the summary from each line: equipment performance and availability, people, and materials. Did each line do what it said it would do? Do the lines have what they need for the next period? Low-stock signals surface here. Items that cannot be resolved within operations are identified and brought to Tier 3 with a proposed path forward.

Maintenance Tier 2 consolidates the maintenance schedule position across areas. The focus for the Integrated Schedule is adherence to the maintenance plan and the forward schedule: what was completed, what is open, what has moved, and what requests have come in to change planned work. Any changes to the maintenance plan that affect production access, resource, or the forward schedule, and that cannot be approved within the maintenance function, are brought to Tier 3 for a decision.

Both Tier 2 meetings feed into Tier 3. Neither resolves what the other owns.

Tier 3 — leaders come together with recommendations, gaps, and questions for resolution. Operations brings any unresolved gaps from the production meeting at Tier 2. Maintenance brings their consolidated schedule position, including any unresolved requests to change planned work and any impacts on production. In addition Procurement reviews material availability against the forward schedule, lead times, and any supply risks.

One schedules, three views. Cross-functional conflicts, between what production needs, what maintenance has planned, and what procurement can deliver, are resolved here, with named owners and a revised plan before the meeting ends. What cannot be resolved at Tier 3 is escalated.

The site's position in the wider planning and scheduling process of the company (e (Sales and Operations Planning (S&OP) or Integrated Business Planning (IBP) is confirmed at Tier 3. The site does not send an estimate. It sends a plan.


Key Considerations

The fixed window

The fixed window is the period within which the schedule is protected from change. Inside it: no changes without a formal exception process and a named decision-maker. Outside it: normal planning and adjustment.

The length of the window is set by the operation, typically one to four weeks for production, longer for procurement where lead times demand it. The window is not a bureaucratic rule. It is the mechanism that makes the schedule believable. A schedule that can be changed by anyone, at any time, for any reason, is not a schedule. It is a starting point for negotiation.

Low stock and out of stock

Low-stock and out-of-stock thresholds are defined for every critical material and finished good. When a threshold is breached, it surfaces in the daily review the same day, not in a weekly report, not in a monthly summary. A named owner is assigned. A plan is in place before the review ends.

Low stock is a warning. Out of stock is a failure. The system is designed to act on the warning.

Thresholds are not arbitrary minimums. They are set against defined safety stock targets, the calculated buffer that reflects demand variability, lead times, and the consequence of running out. A threshold set too low gives no time to act. A threshold set too high ties up cash and space without reason. Both are planning failures.

Safety stock targets are reviewed on a defined cycle. Demand patterns change. Lead times change. The consequence of a stockout changes. A target that was right twelve months ago may not be right today. The review is not a one-time exercise, it is a recurring responsibility of the Planning pillar, with sign-off from the functions who own the demand signal and the supply chain.

Inventory management

The Planning pillar tracks inventory as a measure of planning health, not just a warehouse metric. The right question is not how much inventory the site holds, it is whether the inventory held is the right inventory, in the right place, at the right time.

Excess inventory of the wrong product is a planning failure. It means the schedule produced what was convenient rather than what was needed. It ties up cash, consumes storage space, creates handling cost, and in some cases creates expiry or obsolescence risk.

Insufficient inventory of the right product is also a planning failure. It means the schedule did not anticipate demand, did not protect against variability, or did not act on the low-stock signal in time.

The target is not zero inventory. The target is inventory that reflects the plan, held at the level the safety stock calculation requires, for the products the demand signal says are needed next. Days on hand (the number of days of supply currently held) is a useful measure of whether inventory is tracking in the right direction. It is reviewed alongside schedule adherence and low-stock events as part of the daily and weekly picture.

Production sequence

The order in which products are made matters as much as the volume. A schedule that produces the right total quantity but in the wrong sequence creates the same stockout and excess inventory problems as a schedule that produces the wrong quantity.

The constraint, the line, machine, or resource that limits the rate of the whole operation, should be scheduled first. Everything else is built around it. When the constraint is planned to meet what the customer needs next, and the rest of the schedule is sequenced to support it, the operation produces what is needed in the order it is needed. When the constraint is planned to maximise output or minimise changeovers, the operation produces what is easiest — and the customer waits for what they actually need.

Sequence is reviewed as part of the forward schedule at Tier 3. Changes to sequence inside the fixed window follow the same exception process as any other schedule change.

⚠️
Production sequence is also important from a line clean and ramp up stand point. Moving from Product A to Product B might not require a deep clean, but from Product A to Product C does. Similarly a packaging change that maintains the same product dimensions might have a significantly shorter change over and ramp up time. The role of your production schedulers is to understand these constraints and build them into your optimal schedule where possible.

Master data integrity

The schedule is only as good as the data it is built on. Run rates, cycle times, batch formulas, yields, and material quantities are the foundation of every plan the pillar produces. When that data is wrong, the schedule built on it is wrong, and no amount of daily review fixes a plan that started from a false picture.

Master data is a shared responsibility. Operations knows what the line actually runs. Engineering knows what the process is designed to produce. Procurement knows what the material specification requires. But shared responsibility without a defined process means nobody owns the review, and the data drifts quietly until the gap between what the system says and what the operation does becomes too large to ignore.

The Planning pillar owns the process to review and approve master data. Not the data itself, that belongs to the functions who generate and use it. But the cadence, the method, and the sign-off. On a defined cycle, the key parameters are reviewed against actual performance. When actual results diverge consistently from the planned rate, that is a signal the data needs updating, not that the team is underperforming.

The review asks two questions that mirror the daily schedule review:

  • Does what the system says match what the operation actually does?
  • Does what the system says still reflect what the process is designed to do?

When the answer to either is no, the data is updated, the change is approved, and the schedule is rebuilt on the corrected foundation. The approval requires sign-off from the functions who own the data , Operations, Engineering, Procurement, and is recorded. A change to master data without a record is a change nobody can trace when the next discrepancy appears.

⚠️
Finding a data gap and solving it with a work around is very common. ERP systems that are used to feed an Excel sheet that has real run rates, or change over times. Adding in additional buffers because you know the data does not reflect reality. Part of the purpose of the Pillar is to ensure that we have one version of the truth, one system of truth and that we fix the source, not manage the output.

Capabilities

Process capabilities

The Planning pillar builds capability in three areas:

  • Building the schedule, producing an integrated plan that covers production, maintenance, and procurement, sequenced correctly, anchored to what is actually needed, and built on accurate master data
  • Monitoring and maintaining the schedule, reviewing the plan daily at every tier, acting on gaps the same day, protecting the fixed window, and managing exceptions through a named decision-maker
  • Monitoring and maintaining master data, owning the review and approval process for the data the schedule is built on, so that when actual performance diverges from the plan, the root cause is found in the data rather than managed around it

People capabilities

  • Operations line leaders who can review the production schedule at the line, answer both questions, and escalate when the plan is at risk
  • Operations area leaders who can hold the production schedule across lines and shifts and consolidate the Tier 1 picture for Tier 3
  • Maintenance area leaders who can confirm planned work, resource, parts, and access — and bring a clear position to Tier 3
  • Operations and maintenance site leaders who can hold the full site schedule and represent a confirmed position to the business
  • Procurement leads who can translate the forward schedule into material requirements with lead times applied, and surface supply risks before they become shortages
  • Schedulers and planners who can build and maintain a credible integrated schedule that production, maintenance, and procurement can all work from

Behaviours

The weekly schedule is built on Monday. By Thursday it looks nothing like the plan.

Without the system: Production has been running the same product for four days. A changeover was pushed back twice, once for a maintenance slot given back to production, once because the material had not arrived. Volume is on track. Two products customers needed this week have not been made. One is at low stock. The other is out. Nobody decided this would happen. The schedule just responded to each day's pressure.
With the system: The schedule is built around what is needed next, in the right sequence. The fixed window protects it. Maintenance slots are confirmed before they are locked. Procurement acts on the signal when it is foreseeable. When something disrupts the plan, it is visible the same day, owned by a named person, acted on before it cascades into the following week.

A product is running low. The line manager finds out when the line stops.

Without the system: The low-stock signal was in last week's report. Nobody acted on it. The material was on order but the lead time was longer than the gap. The line stops. An expedite order is placed at premium cost. Production switches to something else while they wait.
With the system: The threshold is set against a calculated safety stock target. When it is breached, it surfaces in the daily review the same day, not in a weekly report. A named owner is assigned before the meeting ends. The response is in place before the line is at risk.

What Good Looks Like

At the line — Tier 1

There are multiple Tier 1 meetings, one per line / key equipment. Operations and the area maintenance person both attend each one.

  • Operations reviews the production schedule for that line: what was planned, what was completed, what is open for this shift and the next
  • Maintenance reviews their planned work for the area: slot availability, access, parts, and resource confirmed
  • Both answer both questions before the meeting ends: did we do what we said, do we have what we need
  • What can be resolved at the line is resolved here. What cannot is escalated, named, with an owner, before the meeting ends
  • If a production delay puts a maintenance slot at risk, it is named in this meeting, not discovered when maintenance arrives and the line is still running

Consolidating the picture — Tier 2

Tier 2 runs as two parallel meetings, each consolidating the outputs from their Tier 1s.

Operations Tier 2:

  • Brings together the summary from each line: equipment performance and availability, people, and materials
  • Confirms which lines did what they said they would do, and which did not , with a clear reason for each gap
  • Surfaces low-stock signals and confirms a named owner and response plan before the meeting ends
  • Identifies items that cannot be resolved within operations and brings them to Tier 3 with a proposed path forward, not a list of problems, a position

Maintenance Tier 2:

  • Consolidates the maintenance schedule position across areas: completed, open, moved, and any requests to change planned work
  • The focus for the Integrated Schedule is adherence to plan and the forward schedule
  • Any request to change planned maintenance that affects production access, resource, or the forward schedule is identified here and brought to Tier 3 for a decision
  • Arrives at Tier 3 with a clear position, what is confirmed, what needs a decision, and what the recommendation is

Resolving what Tier 2 could not — Tier 3

Leaders come together with the consolidated picture from both Tier 2 meetings, plus procurement's view of material availability and supply risk.

  • Operations presents the site production position
  • Maintenance presents their consolidated schedule position, including any unresolved requests to change planned work
  • Procurement presents material availability, lead time risks, and any supply constraints against the forward schedule
  • Cross-functional conflicts are resolved here, in the room, with named owners and a revised plan before the meeting ends
  • The site's confirmed position in the S&OP / IBP cycle is agreed here, not an estimate, a plan
  • What cannot be resolved at Tier 3 is escalated, named, with an owner and a timeline

Audits and Confirmations

✅
Is the schedule being built around what is needed, or what is easiest to make? Look at the last four weeks of production. Does the sequence reflect customer demand and inventory position, or does it reflect long runs and avoided changeovers? If the same product appears in extended runs while others go short, the schedule is optimising for the wrong thing.
✅
Is the fixed window being held? Count how many changes were made inside the fixed window last week. One or two with a named exception is a system working under pressure. Five or more with no formal process is a schedule that nobody believes. If the window is not being held, find out why, the cause is usually upstream, not in the planning function.
✅
Are low-stock thresholds triggering a same-day response? Pull the last three low-stock events. When did the threshold breach? When was it acted on? If the answer is days later, or at the weekly review, the signal is arriving but not travelling. The threshold is working. The escalation is not.
✅
Are safety stock targets set against a calculation, or a habit? Ask the planning team how the current safety stock levels were set and when they were last reviewed. If the answer is "we've always held that level" or "we added a buffer after the last stockout," the targets are not calculated, they are inherited. Demand variability and lead times should drive the number, reviewed on a defined cycle.
✅
Is master data reviewed on a defined cycle, or only when something breaks? If the last master data review was triggered by a schedule failure rather than a calendar date, the process is reactive. Ask when run rates, cycle times, and yields were last validated against actual performance. A gap of more than six months in a changing operation is a gap that is already affecting the schedule.
✅
Is the site's position in the S&OP / IBP cycle based on a confirmed schedule? Ask what the site submitted in the last cycle. If the answer is last month's actuals, an estimate, or a number from the planning system that has not been validated against current capacity and constraints, the site is not participating in the cycle, it is reporting into it.
✅
Is customer service tracked as a planning output? If a service failure is reviewed only by logistics or commercial, the planning root cause will not be found. Ask whether the last three service failures were investigated for schedule cause. If not, the planning system has no feedback loop from its most important output.

Phases

Phase 1 — Establish

The Integrated Schedule is introduced for the pilot area. Production scheduling is confirmed daily at Tier 1. The fixed window is defined and agreed. Low-stock thresholds are set for critical materials, anchored to initial safety stock targets, not arbitrary minimums. The two questions are established as the daily standard.

Maintenance scheduling is added at Tier 2, slots confirmed with resource and materials before they are locked. The connection between the site schedule and the S&OP / IBP cycle is mapped, even if it is not yet fully formalised. Production sequence is reviewed for the pilot area, the constraint is identified and the schedule is built around it.

Phase 2 — Strengthen

The Integrated Schedule extends to all lines and departments. Procurement scheduling is added at Tier 3, material requirements generated from the schedule with lead times applied. The S&OP / IBP interface is formalised: defined inputs, defined outputs, defined frequency, named owners at each level.

Safety stock targets are reviewed and confirmed for all critical materials and finished goods. Inventory management, days on hand, excess, and shortfall, is tracked as a planning measure alongside schedule adherence. Customer service is tracked as a planning output: a service failure that traces to a schedule decision is investigated as a planning failure.

Schedule adherence, customer service, and low-stock management are confirmed processes, audited, owned, and improving.

Phase 3 — Sustain

The Integrated Schedule runs across the site. The fixed window is held. Low-stock events are rare and acted on immediately when they occur. Safety stock targets are reviewed on a defined cycle and updated when demand patterns or lead times change. Inventory reflects the plan, not what was convenient to make. The site's position in the S&OP / IBP cycle is based on a confirmed schedule. The planning capability is assessed, refreshed, and built into how the site runs, not a project, not a programme. Just how we plan.